Cashew Import Checklist

29 checks across five stages, with a planning allowance for each. Work it backwards from the date the goods must be usable, not forwards from today.

0 of 29 doneTicks are not saved anywhere. Print the page if you need a record.

Before you contract

Allow about 2 weeks on a first shipment with a new processor.

Contract

Allow about 1 week on a first shipment with a new processor.

Production and pre-shipment

Allow about 5 weeks on a first shipment with a new processor.

Documents

Allow about 1 week on a first shipment with a new processor.

In transit and arrival

Allow about 6 weeks on a first shipment with a new processor.

Need a price for this grade?

Send the requirement. We reply within 24 business hours with one detailed quote for the packed kernels.

Request a quote

Working the timeline backwards

Take the date the goods must be usable in your warehouse. Subtract clearance and testing, then sailing, then loading, then approval, then production, then contracting.

About 15 weeks is a fair planning figure for a first container. A repeat shipment on an approved spec runs several weeks shorter, because sample approval collapses and production is scheduled rather than negotiated.

  • ArtworkThe most common two week loss. Start it before the raw nuts are booked.
  • Certificate scopeThe second. Verify during supplier checks, not during shipment.
  • A document detailThe third. A corrected certificate has to travel back through the issuing body.
  • TetVietnamese factories and ports slow around Lunar New Year, and the effect starts before the holiday.
  • Peak seasonSpace, not production, is the constraint on the trans-Pacific and Asia to Europe lanes from roughly August.